Dakota Electric ASSOCIATION
Energy Center TIMELINE
From assessing the current facility to the design and build of a new Energy Center, follow along as we prepare for tomorrow. Details will be updated as the project progresses. Have questions? Please visit our FAQ page.
Project Schedule
Phase 4: Construction
Timeframe
July 2025 – Spring 2027
Status
In Progress
More Information
Phase 4 includes the physical construction of the new headquarters facility. It is divided into six sub-phases covering all core structural and finish components of the project. No additional board approvals are required for this phase to proceed.
Timeframe
July 2025 – Spring 2026
Status
In Progress
More Information
This phase includes the installation of concrete foundations for all major buildings on site. It establishes the structural base needed to support each facility and is the first physical construction activity on the new campus.
Timeframe
Fall 2025 – Summer 2026
Status
Not Yet Started
More Information
During this phase, structural steel frameworks will be erected for all buildings. This stage forms the skeleton of the facility, allowing the overall scale and layout to take shape above ground.
Timeframe
Winter 2026 – Summer 2026
Status
Not Yet Started
More Information
This phase includes the installation of building exteriors, such as walls, windows, and roofing systems. Once complete, each structure will be fully enclosed and protected from the elements.
Timeframe
Spring 2026 – Winter 2026
Status
Not Yet Started
More Information
This phase includes the interior walls and framing systems. It defines rooms, corridors, and operational areas within the building, setting the stage for mechanical systems and finishes.
Timeframe
Spring 2026 – Fall 2026
Status
Not Yet Started
More Information
This phase focuses on developing exterior areas of the site, including parking lots, driveways, green spaces, and landscaping. It enhances site accessibility and begins establishing the finished campus appearance.
Timeframe
Summer 2026 – Spring 2027
Status
Not Yet Started
More Information
The final construction phase involves completing interior elements such as drywall, flooring, lighting, cabinetry, and final painting. This stage prepares the facility for occupancy and operational readiness.
Phase 3: Facility Design
Timeframe
November 2024 -Spring 2025
Board Action
Approved May 2025
Status
Completed
More Information
The board of directors will approve Phases 3A – 3C separately before moving to Phase 4.
Timeframe
November 2024
Board Action
Approved
Status
Complete
More Information
Phase 3A of the facility design was completed and approved by the board of directors to move to Phase 3B.
Timeframe
November 2024 – Spring 2025
Board Action
Approved
Status
Complete
More Information
Phase 3B of the facility design was completed and approved by the board of directors to move to Phase 3C.
Timeframe
January – Spring 2025
Board Action
Approved
Status
Complete
More Information
Phase 3C of the facility design will be completed and approved by the board of directors to move to Phase 4.
Phase 2: Land Acquisition
Phase 1: Facility Planning Study
Timeframe
October 2019 – March 2024
Board Action
Approved
Status
Complete
Outcome
A formal Needs Assessment was established.